The construction of Poklonnaya 9 is on schedule

11

The Poklonnaya 9 apartment complex maintains a high rate of construction.

Facade work completed by 55%. For the complex, a window profile of the German company Schüco and Crystalvision glass were chosen, which are distinguished by maximum neutrality and the highest level of color rendering, as well as a slight mirror effect.

Interior work continues in the building on the installation of vertical structures, finishing of common areas and installation of doors.

Specialists have completed 60% of the work on the installation of mechanical engineering systems, the connection of electrical systems continues.

All materials and components for the main construction work and interior decoration, and elevator equipment were ordered and paid for in advance and already delivered to the construction site, so today the company has all the necessary components for the stable implementation of the project.