Construction news "Poklonnaya 9"

13

With the advent of autumn, the facades of the Poklonnaya 9 apartment complex sparkled with new colors. Reflection of the mood of the city was made possible thanks to German Schüco window profiles with Belgian Crystalvision glasses, which have a mirror effect. In general, the installation of the facade is almost 80% completed, at the moment the first floors of the building are being faced with natural stone. Roofing works are 40% completed.

Works on the installation of elevator equipment are almost completed - 93%, mechanical engineering systems are installed by 65%, electrical communications are half done. Interior decoration is more than 65% completed, 44% of the apartments have doors installed.

 