Summer report on the construction of Poklonnaya 9

11

Summer in Moscow is very changeable, but this does not affect the construction of the Poklonnaya 9 apartment complex, which is in full accordance with the implementation schedule.

Facade works are almost 70% completed. German aluminum profiles and Schuco windows were chosen for the apartments, Belgian Reynaers glazing systems will be installed in the penthouses.

Since all the lots in the complex are rented with a ready-made designer finish, in parallel, specialists are working inside the apartments. 75% of the works on the installation of mechanical engineering systems and partitions have been completed, in 35% of the lots entrance doors have already been installed.

Installation of elevator equipment is at the finish line - readiness of 83%.